Easily configure the columns with the information you want to see in your Gantt.
In the Gantt there are several columns with information about your activities, which you can activate or deactivate whenever you want in the checkbox next to each item, leaving visible only what you need.
Available options include:
- ID: Corresponds to the number assigned by ProPlanner to each of the activities.
- Activity: Name given to the activity.
- Status: Indicates if the activity is behind schedule (red), ahead of schedule (blue), completed (green check) or if it is not yet appropriate to execute it (-).
- Start: Start date of the activity according to the schedule
- Duration: Number of days that an activity is scheduled
- End: End date of the activity according to the schedule
- Progress: Percent progress of the activity
- Projected Progress: Expected progress that the activity should have according to the baseline schedule of the project.
- Free Float: Corresponds to the days of float that an activity has for its execution with respect to its successor activities.
- Total Float: Corresponds to the days of float that an activity has for its execution with respect to the end of the project.
- Predecessors: Indicates the dependency relationships that the activity has with respect to its predecessor activities. Learn more in Links between activities .
- Successors: Indicates the dependency relationships that the activity has with respect to its successor activities.
- Constraint Type: Indicates the type of constraint that the activity has. Learn more at Types of Date Restrictions .
- Calendar: Shows the calendar assigned to the activity. Learn more in How to set up a calendar?
- Constraint Date: Indicates the date of the constraint associated with the activity.
- Man-Hours Earned: Corresponds to man-hours earned according to the percentage of progress of the activity.
- Man-Hours Budgeted: Shows the number of man-hours assigned to an activity.
- Cost Budgeted: Indicates the cost assigned to an activity.
- Cost Spent: Indicates amount used to execute the activity.
- Cost Earned: Indicates the cost earned according to the percentage of progress of the activity.
- Weight: Shows how much an activity is weighted within the master activity that contains it.
- Critical Path: Indicates whether or not the activity belongs to the critical path of the project.
- Baseline Start: Start date of the activity according to its baseline.
- Baseline End: End date of the activity according to its baseline.
- Baseline Progress: Expected progress that the activity should have according to its baseline.
- Baseline Man-Hours: Shows the amount of base work for an activity. Corresponds to the amount that was in the "Man Hours Budgeted" column at the time the baseline was saved .
- Baseline Cost: Shows the base cost of an activity. Corresponds to the amount that was in the "Cost Budgeted" column at the time the baseline was saved.
- Baseline Duration: Days that an activity lasts according to its base line.
- Responsible: User assigned to an activity
- Company: Company assigned to an activity
- Tags: Custom tags used to organize activities