Control Criteria for my Project

In ProPlanner you can configure the control criteria for your projects. For this, you must go to Settings > Project Settings .

  1. Planning Day: Planning day marks the beginning of each week of your project . So if your planning day is Monday, your project week will be Monday through Sunday. You must take this into consideration for the management of commitments and progress entry to tasks.
  2. Task Weight Criteria: You can configure the weighting of your tasks for the project based on the duration, cost or man-hours of the activity to which the tasks belong.
  3. PRR Goal: Set your Percent Roadblocks Removed goal , in this way you can check in analytics each week if said goal is being met.
  4. Progress Curve Criteria: Configure the display of your S-curve, you can choose duration, cost or man-hours , depending on the criteria you want to control.
  5. PPC Goal: Percent Plan Complete will help you monitor how reliable your weekly planning is. Set your goal to check in analytics every week if said goal is being met.
Release Roadblock Criteria: The option to make commitment dates “editable” or “not editable” in the Lookahead module