Copy/Paste Activities

Now you can easily copy/paste activities in your Master Plan!

In the Master Plan, you can perform the following actions:

  • Copy Activities:  To do this you must select the activities that you want to copy, and then press "ctrl+c". 
  • Paste Activities: To do this you must select the activity in which you want to paste your copied activities under. Then you just have to press "ctrl+v".

Aug-25-2022 15-35-52

Both when copying and pasting, you will receive a notification that the action has been completed successfully. 

Screen Shot 2022-08-25 at 3.36.48 PM

Special Note:

  • You can copy and paste between different stages and projects.
  • Pasting activities maintains the display level, or indentation, of the marked activity.
  • When copying and pasting, the following information will be kept:
    • Name of the activity
    • Start date
    • Duration
    • End Date
    • Links between copied activities
    • Calendar (*)
    • Cost
    • Responsible
    • Company
    • tags
    • Description

(*) If activities are copied to a project with a different calendar, these activities will be assigned the Default Calendar of the sector.