How to commit the following week from the Lookahead?
Now you can commit the following week after the current week has been closed out.
Before committing the following week, it is important to first ensure that:
- The current week that has been committed is now closed.
- All the tasks scheduled for the upcoming week appear in the planning period.
- Ensure that the tasks have been assigned the correct dates, responsible users, and companies.
- The "Weekly Commitment" column should align with the planned work.
The following week can only be committed once the current week has been closed out. The following week can only be progressed and closed out once it is in the current planning period.
As shown below, once the current week has been closed out in the Weekly Plan, the Lookahead module allows you to commit the following week.