Check the reliability of your committed weekly plans.
The Percent Plan Complete (PPC) corresponds to a reliability indicator, which represents how many of the commitments acquired for each week were actually fulfilled.
For example, if a task had a progress commitment of 70% and its actual progress at the end of the week was 73%, then it is considered accomplished.
The calculation of the PPC is simple:
For example, if in a week 10 tasks were committed and 8 of them were fulfilled, then:
In Analytics you can view the PPC of your project , which is represented by a bar graph. When you move the cursor over each of the bars, you will be able to see the details of the corresponding week (PPC, completed tasks and committed tasks).