How to View and Edit Project Work Hours

The "Work Hours" in Outbuild refers to the number of hours that will represent a day of work in our activity durations.

 

You can navigate to the work hours by clicking on the clock icon in the Calendar settings.

 

The Outbuild default for work hours is 8 hours per day, 40 hours per week. 

 

Both "Hours per day" and "Hours per week" can be modified if needed; however, they typically remain unchanged in most situations.

 

In the example below, the shift hours have been changed which does require updating the work hours. 

 

The shift hours reflect a 9 hour shift instead of the default 8 hours, so the work hours need to be updated to 9 hours per day, 45 hours per week. 

After making the necessary adjustments, be sure to click the "Save" button to apply the changes.

 

If the work hours do not match the shift hours, this will result in decimals in schedule and skewed durations.