PRR Graph

Review each week the percentage of roadblocks removed.

The Percentage of Roadblocks Removed (PRR) corresponds to a reliability indicator, which represents how many of the roadblocks committed for a week were removed before their commitment date .

The calculation of the PRR is similar to that of the PPC :

 

For example, if for a week there were 10 committed Roadblocks and 9 were removed, then:

In Analytics you can review the PCR of your project, which is represented in a bar graph. To review the PCR of a particular week, you just have to hover over the corresponding bar.

Learn more about restrictions in How to manage and release restrictions?