In ProPlanner you can easily modify the dates and durations of the activities in your Master Plan.
To keep the monitoring updated, you must reschedule the activities of your Master Plan so that they adjust to their actual dates of execution. For this there are two movements:
- Drag the activity bar, which will keep the duration, but change the start and end dates.
- Stretch or contract the ends of the activity bar, which allows you to modify the start and end dates independently.
Also, you can edit the start date and duration of the activities of your Master Plan in the table..
Note: The activities that have already entered a partial progress cannot modify their start date, only their duration will be editable, since it is understood that they have already started to be executed. While the completed ones will not be editable.
Remember:All progress changes must be saved.