S-Curve

Review the progress of your project over time.

In the S-Curve graph you can see:

  • Baseline Curve (blue): Shows the progress corresponding to the active baseline of your project.
  • Follow-up Curve (orange): Shows the progress according to the impacted Master Plan, based on the rescheduling that has been carried out.
  • Real Curve (green): Shows the advances actually entered each week.

To view the progress of a particular week (baseline, follow-up or real) you just have to place the cursor on the curve you want to view and on the corresponding week.

Curva S

Remember that the S-Curve of your project is built based on the control criteria that you have configured (duration, man hours, or cost). Learn more in Control criteria for my project.