Review the progress of your project over time.
In the S-Curve graph you can see:
- Baseline Curve (blue): Shows the progress corresponding to the active baseline of your project.
- Follow-up Curve (orange): Shows the progress according to the impacted Master Plan, based on the rescheduling that has been carried out.
- Real Curve (green): Shows the advances actually entered each week.
To view the progress of a particular week (baseline, follow-up or real) you just have to place the cursor on the curve you want to view and on the corresponding week.
Remember that the S-Curve of your project is built based on the control criteria that you have configured (duration, man hours, or cost). Learn more in Control criteria for my project.