See how fast your project is going compared to planned progress.
Speed is an indicator that will allow you to know how fast your project is going with respect to the progress of work planned for each period. In other words, the real progress made in a period is compared with the progress that should have been made according to the baseline for the same period.
The values recorded in the speed curve are generated weekly, according to the configured periods (each project has a planning day configured that marks the beginning of each week).
On the graph, 2 curves are displayed:
- Goal: Represents the ideal speed (indicated by the speed value = 1 in green), that is, the project progresses as planned by the baseline.
- Speed: Shows the registered speed, each point of the curve represents a week of the project.